P- 6 APIPE- XXXCONN.TO SUPPLY SYST. |
$1.00 |
$20.00 |
$20.00 |
$0.00 |
|
P- 6 DPIPE- XXXIRRIGATION SYSTEM |
$4.00 |
$48.00 |
$48.00 |
$0.00 |
|
P- 3B SITE- XXXSITEWORK-SEWER &/STORM |
$1,000.00 |
$50.00 |
$50.00 |
$0.00 |
|
B- 2B APPL- XXXBLDG SFR APPL FEE |
$1.00 |
$750.00 |
$750.00 |
$0.00 |
|
P- 2 FIXTU- XXXPLUMBING FIXTURES |
$20.00 |
$300.00 |
$300.00 |
$0.00 |
|
B- 3 BLDG - XXXBUILDINGS |
$3,772.00 |
$200.00 |
$200.00 |
$750.00 |
50145 9/12/2009 |
P- 3A SEWE- XXXSEWER CONNECTIONS |
$1.00 |
$50.00 |
$50.00 |
$0.00 |
|
B- 7 FLATW- XXXALL FLATWORK/DECKS GRD |
$2,554.00 |
$75.00 |
$75.00 |
$0.00 |
|
E- 3A OUT - XXXELECT OUTLETS GENERAL |
$2,450.00 |
$250.00 |
$250.00 |
$0.00 |
|
E- 3B OUT - XXXELECT OUTLETS APPLIANC |
$13.00 |
$130.00 |
$130.00 |
$0.00 |
|
E- 3C OUT - XXXELECT LIGHT EXTERIOR |
$13.00 |
$130.00 |
$130.00 |
$0.00 |
|
B-21B FILL- XXXSEAWAL/RIPRAP/FIL/DCK APPL |
$1.00 |
$80.00 |
$80.00 |
$0.00 |
|
E- 4B SERV- XXXSINGLE PH 0-300 AMP |
$1.00 |
$50.00 |
$50.00 |
$0.00 |
|
E- 4A SERV- XXXELECT TEMPORARY SERVIC |
$1.00 |
$50.00 |
$50.00 |
$0.00 |
|
B-21A FILL- XXXFILL- LAND &/OR WATER |
$128.00 |
$65.00 |
$65.00 |
$0.00 |
|
E- 9B A/C - XXXCENTRAL A/C < 20 TONS |
$2.00 |
$100.00 |
$100.00 |
$0.00 |
|
E-13 ALRMR- XXXALARM SYST.RESIDENTIAL |
$1.00 |
$50.00 |
$50.00 |
$0.00 |
|
M- 2 1A/C - XXX0-2 TON |
$1.00 |
$50.00 |
$50.00 |
$0.00 |
|
M- 2 2A/C - XXXOVER 2 TON TO 5 TON |
$1.00 |
$65.00 |
$65.00 |
$0.00 |
|
M- 3 DUCTW- XXXDUCT WORK |
$22.00 |
$220.00 |
$220.00 |
$0.00 |
|
B- A PLAN- XXXPLAN REVIEW BLD NEW SFR |
$1.00 |
$100.00 |
$100.00 |
$0.00 |
|
B- D TRNF- XXXTRANSFER BLDG.PERMIT |
$1.00 |
$200.00 |
$200.00 |
$0.00 |
|
ROGO - SFR ROGO FEE |
$1.00 |
$200.00 |
$200.00 |
$0.00 |
|
R- 9A ROOF- XXXROOFING- REPAIRS/NEW |
$3,343.00 |
$170.00 |
$170.00 |
$0.00 |
|
B- BIO EDU- BIO EDUCATION RIRAP/CAN RS/RS |
$1.00 |
$10.00 |
$10.00 |
$0.00 |
|
B- F TRNF- EXT PERMIT FOR 180 DAYS |
$1.00 |
$250.00 |
$250.00 |
$0.00 |
|
LDR 1-SFR- XXXNEW PLAN REVIEW SFR/MH |
$1.00 |
$75.00 |
$75.00 |
$0.00 |
|
LDR FEMA - XXXPLAN REVIEW FLOODPLAIN MAJ |
$1.00 |
$140.00 |
$140.00 |
$0.00 |
|
CO-RES - XXXC.O.FEE- RESIDENTIAL |
$1.00 |
$100.00 |
$100.00 |
$0.00 |
|
ZONING-032- ADMINISTRATIVE RELIEF |
$1.00 |
$1011.00 |
$1,011.00 |
$0.00 |
|
BI -SITE - XXXSITE VISIT BIO PERMITTING |
$2.00 |
$260.00 |
$260.00 |
$0.00 |
|
LDR 1P SFR- XXXNEW PLAN REVIEW SFR/MH |
$1.00 |
$75.00 |
$75.00 |
$0.00 |
|
T- 2 - XXXTECHNOLOGY FEE >$500 |
$1.00 |
$20.00 |
$20.00 |
$0.00 |
|
EDUCATION - NEW RES OR NEW COMM |
$1.00 |
$25.00 |
$25.00 |
$0.00 |
|
CONT-INVES- CONTRACTOR INVESTIGATO |
$1.00 |
$11.00 |
$11.00 |
$0.00 |
|
PLAN ED - XXXPLANNING EDUCATION FEE |
$1.00 |
$10.00 |
$10.00 |
$0.00 |
|
3A-I F - FIRE/EMS IMP SFR/NEW |
$1.00 |
$105.00 |
$105.00 |
$0.00 |
|
3A-I L U.K- *DO NOT USE LIBRARY IMP |
$1.00 |
$242.00 |
$242.00 |
$0.00 |
|
DCA RE ED - SURCHARGE DCA(.10%)BLDG FEE |
$2,998.00 |
$4.50 |
$4.50 |
$0.00 |
|
3A-I P - PARKS IMP SFR/NEW UPPE |
$1.00 |
$340.00 |
$340.00 |
$0.00 |
|
3A-I R - ROADS IMP SFR/NEW UK |
$1.00 |
$633.00 |
$633.00 |
$0.00 |
|
3A-I S - *DO NOT USE SHERIFF IMP SFR/UK |
$1.00 |
$150.00 |
$150.00 |
$0.00 |
|
3A-I W - *DO NOT USE WASTE IMP SFR/PK |
$1.00 |
$64.00 |
$64.00 |
$0.00 |
|
DCA - SURCHARGE DCA(.90%)BLDG FEE |
$2,998.00 |
$40.47 |
$40.47 |
$0.00 |
|
DBPR - SURCHARGE DBPR(1.35%)BLDG FEE |
$2,998.00 |
$40.47 |
$40.47 |
$0.00 |
|
DBPR RE ED- RETAINED DBPR ED(.15%)BLDG FEE |
$2,998.00 |
$4.50 |
$4.50 |
$0.00 |
|
PL -SITE - XXXSITE VISIT PLANNING PERMIT |
$1.00 |
$130.00 |
$130.00 |
$0.00 |
|
DBPR 2 - SURCHARGE DBPR(1.35%)BLDG FEE |
$6,975.28 |
$94.17 |
$94.17 |
$0.00 |
|
DBPR ED 2 - RETAINED DBPR ED(.15%)BLDG FEE |
$6,975.28 |
$10.46 |
$10.46 |
$0.00 |
|
REVCORPG - XXXNUM OF CORRECTION PLAN PGS |
$15.00 |
$150.00 |
$150.00 |
$0.00 |
|
0ABLDRNS - 50%APP REV NW REPL BLD 5PR |
$422,351.00 |
$3487.64 |
$3,487.64 |
$0.00 |
|
0BBLDRNS - 50%ISS REV NW REPL BLD 5PR |
$422,351.00 |
$3487.64 |
$3,487.64 |
$0.00 |
|
0BENVRNS - 100%ISS REV NW REPL ENV |
$422,351.00 |
$1708.62 |
$1,708.62 |
$0.00 |
|
0BPLNRNS - 100%ISS REV NW REPL PLN |
$422,351.00 |
$1731.03 |
$1,731.03 |
$0.00 |
|
DCA 2 - SURCHARGE DCA(.90%)BLDG FEE |
$6,975.28 |
$94.17 |
$94.17 |
$0.00 |
|
DCA ED 2 - SURCHARGE DCA(.10%)BLDG FEE |
$6,975.28 |
$10.46 |
$10.46 |
$0.00 |
|